# EXECUTE: Update Implementation Plan
**IMPORTANT: This is an EXECUTION command. Immediately perform all steps below without waiting for confirmation.**
Re-plan based on actual progress, calculate velocity, identify blockers, and adjust sprint allocations.
## STEP 1: Prerequisites Check
First, check if IMPLEMENTATION_PLAN.md exists:
```bash
ls docs/IMPLEMENTATION_PLAN.md
```
If missing:
```
❌ Error: docs/IMPLEMENTATION_PLAN.md not found
Please run:
claude generate-implementation-plan
Then try update-plan again.
```
## STEP 2: Read Current Plan
Read `docs/IMPLEMENTATION_PLAN.md` and extract:
### Metadata:
- **Team Size**: How many developers
- **Sprint Duration**: 2 weeks (standard)
- **Initial Velocity**: Planned SP/sprint
- **Actual Velocity**: Average from completed sprints
- **Total Tasks**: Total count
- **Total Story Points**: Sum of all tasks
### Current Progress:
For each task, extract:
- **Task ID**: e.g., "Task 1.2"
- **Status**: TODO | IN_PROGRESS | BLOCKED | DONE | SKIPPED
- **Estimated**: Hours planned
- **Actual**: Hours spent (if DONE or IN_PROGRESS)
- **Owner**: Team member assigned
- **Sprint**: Which sprint it's in
### Completed Sprints:
For each sprint marked [COMPLETED] or [IN_PROGRESS]:
- **Sprint Number**: 1, 2, 3...
- **Planned SP**: Story points allocated
- **Completed SP**: Story points actually done
- **Velocity %**: (Completed / Planned) × 100%
## STEP 3: Calculate Actual Velocity
### Velocity Formula:
```
Actual Velocity = Average(Completed SP per sprint)
```
**Example**:
```
Sprint 1: 32 planned, 32 completed → 100%
Sprint 2: 32 planned, 26 completed → 81%
Sprint 3: 32 planned, 10 completed → 31% (Week 1 only, not counted)
Average velocity = (32 + 26) / 2 = 29 SP/sprint
```
**Velocity Trend**:
- **Increasing**: Team getting faster (learning curve)
- **Stable**: Consistent delivery
- **Decreasing**: Technical debt, blockers, team issues
### Compare to Planned Velocity:
```
Planned Velocity: 44 SP/sprint (team capacity)
Actual Velocity: 29 SP/sprint
Velocity Ratio: 29 / 44 = 66% (delivering 66% of capacity)
```
## STEP 4: Identify Blockers
### Scan for BLOCKED Tasks:
```markdown
### Task 2.3: API Foundation [BLOCKED]
**Blockers**: Waiting for backend team to deploy staging API
```
### Analyze Blocker Impact:
For each blocker:
1. **What tasks depend on this?** (check "Blocks" field)
2. **Critical path impact?** (is this on critical path?)
3. **Sprint impact?** (will current sprint be delayed?)
4. **Workaround available?** (can we mock/stub?)
**Example**:
```
Blocker: Task 2.3 API Foundation (2 weeks)
Blocks: Task 2.4, Task 2.5, Task 3.1 (3 tasks, 26 SP)
Critical Path: YES (on critical path)
Sprint Impact: Sprint 2 delayed by 1 week
Workaround: Use mock API for UI development (partial mitigation)
```
## STEP 5: Identify Risks and Delays
### Tasks Behind Schedule:
Tasks marked IN_PROGRESS with:
- **Actual > Estimated**: Taking longer than expected
- **Status = IN_PROGRESS for >1 week**: Potentially stuck
**Example**:
```
Task 2.2: Dashboard - Data Layer [IN_PROGRESS]
Estimated: 6 hours
Actual: 10 hours (67% over estimate)
Status: IN_PROGRESS for 5 days
Risk: HIGH (team member may need help)
```
### Sprint Health:
For current sprint:
- **On track**: >80% velocity
- **At risk**: 60-80% velocity
- **Behind**: <60% velocity
## STEP 6: Recalculate Sprint Allocations
### Algorithm:
1. **Use actual velocity** for remaining sprints (not planned)
2. **Respect dependencies** (don't move tasks before their dependencies)
3. **Balance workload** across team members
4. **Add buffer** (20% for unknowns)
**Example**:
```
Remaining work: 192 SP
Actual velocity: 29 SP/sprint
Sprints needed: 192 / 29 = 6.6 → 7 sprints
```
### Re-allocate Tasks:
For each remaining sprint:
1. Start with tasks on **critical path**
2. Fill remaining capacity with **parallel tasks**
3. Ensure each owner has balanced workload
4. Mark dependencies as blockers if not ready
**Example**:
```
Sprint 4 (revised):
- Task 3.1: API Consumer (13 SP) - Carol [was blocked, now unblocked]
- Task 3.2: Dashboard Widgets (8 SP) - Dave
- Task 3.3: Notifications (5 SP) - Eve
- Buffer: 3 SP (20%)
Total: 29 SP (matches actual velocity)
```
## STEP 7: Adjust Timeline Forecast
### Original Forecast:
```
8 sprints (16 weeks) at 44 SP/sprint
Total: 320 SP
```
### Revised Forecast:
```
11 sprints (22 weeks) at 29 SP/sprint
Total: 320 SP
Delay: 6 weeks
```
### Delay Analysis:
```
Original Timeline: 16 weeks
Revised Timeline: 22 weeks
Delay: 6 weeks (38% increase)
Causes:
1. Lower than expected velocity (29 vs 44 SP)
2. Backend API blocker (1 week delay)
3. Task 2.2 complexity underestimated (4 hours over)
```
### Recommendation:
If delay unacceptable:
1. **Reduce scope**: Cut P2/P3 features (save 40 SP → 10 sprints)
2. **Increase team**: Add 1 senior dev (velocity +8 SP → 9 sprints)
3. **Work overtime**: 10% capacity increase (velocity +3 SP → 10 sprints)
4. **Defer polish**: Move non-critical tasks post-launch
## STEP 8: Update Progress Dashboard
### Update Metadata:
```markdown
## Metadata
- **Generated**: 2025-01-15
- **Last Updated**: 2025-02-05 (updated after Sprint 2)
- **Team Size**: 7 developers (2 senior, 4 mid, 1 junior)
- **Sprint Duration**: 2 weeks
- **Planned Velocity**: 44 story points/sprint (team capacity)
- **Actual Velocity**: 29 SP/sprint (average last 2 sprints)
- **Total Tasks**: 87
- **Total Story Points**: 320
- **Original Duration**: 8 sprints (16 weeks)
- **Revised Duration**: 11 sprints (22 weeks)
- **Delay**: 6 weeks (38% behind schedule)
```
### Update Progress Bars:
```markdown
## Progress Dashboard
Sprint 1: ██████████ 100% (32/32 SP) ✅
Sprint 2: ████████░░ 81% (26/32 SP) ✅ (completed)
Sprint 3: ███░░░░░░░ 30% (10/32 SP) ⏳ (Week 1, in progress)
Sprint 4: ░░░░░░░░░░ 0% (0/29 SP) - REVISED allocation
Sprint 5-11: ░░░░░░░░░░ 0% - REVISED timeline
Overall: ████░░░░░░ 40% (128/320 SP completed)
```
### Update Burndown:
```markdown
## Burndown Chart Data
| Sprint | Planned | Completed | Remaining | Trend |
|--------|---------|-----------|-----------|-------|
| Sprint 1 | 32 | 32 | 288 | ✅ On track |
| Sprint 2 | 32 | 26 | 262 | ⚠️ Slight delay |
| Sprint 3 | 32 | 10 | 252 (Week 1) | 🚨 Behind |
| Sprint 4 | 29 (revised) | 0 | 252 | - |
| Sprint 5 | 29 (revised) | 0 | 223 (forecast) | - |
**Trend**: 🚨 Behind schedule (6 weeks delay projected)
**Original Forecast**: 8 sprints (16 weeks)
**Revised Forecast**: 11 sprints (22 weeks)
**Velocity**: 29 SP/sprint (actual) vs 44 SP/sprint (planned)
```
## STEP 9: Update Risk Register
Add new risks discovered during this sprint:
```markdown
## Risk Register
| Task ID | Risk Level | Risk Description | Mitigation | Status |
|---------|------------|------------------|------------|--------|
| 2.3 | HIGH | Backend API delay (1 week) | Use mock API for UI dev | MITIGATED |
| 2.2 | MEDIUM | Complexity underestimated | Pair programming with Bob | IN_PROGRESS |
| NEW | HIGH | Velocity lower than planned (66%) | Reduce scope or extend timeline | OPEN |
```
## STEP 10: Add Recommendations Section
Based on analysis, add recommendations:
```markdown
## Recommendations (Generated 2025-02-05)
### 🚨 Critical Issues:
1. **Velocity Gap**: Delivering 29 SP/sprint vs 44 planned (66% capacity)
- **Cause**: Junior dev learning curve, complexity underestimated
- **Action**: Increase pairing, refine estimates in next sprint planning
2. **Backend Blocker**: API Foundation delayed 1 week
- **Impact**: 3 tasks blocked (26 SP), critical path affected
- **Action**: Switch to mock API for UI work, request backend prioritization
### ⚠️ Timeline Impact:
- **Original**: 16 weeks (8 sprints)
- **Revised**: 22 weeks (11 sprints)
- **Delay**: 6 weeks (38% increase)
### Options to Recover:
1. **Reduce Scope** (Recommended)
- Cut 2 P2 features (40 SP)
- New timeline: 10 sprints (20 weeks)
- Delay reduced to 4 weeks
2. **Add Resources**
- Hire 1 senior developer
- Velocity increases to 37 SP/sprint
- New timeline: 9 sprints (18 weeks)
3. **Extend Timeline**
- Accept 11-sprint timeline
- Communicate delay to stakeholders
- No scope reduction
### Next Steps:
1. Discuss options with Product Manager
2. Review Sprint 3 velocity (Week 2) to confirm trend
3. Update stakeholder review with revised timeline
4. Run `claude update-plan` again after Sprint 3 completes
```
## STEP 11: Update Sprint Sections
For each sprint, update:
- SP allocations (use actual velocity)
- Task assignments (rebalance based on progress)
- Status markers ([COMPLETED], [IN_PROGRESS], [TODO])
**Example**:
```markdown
## Sprint 4: Advanced Features (Week 7-8) - 29 SP [TODO] - REVISED
### Task 3.1: API Consumer - Dashboard Data [TODO]
**Owner**: Carol (Mid) | **Story Points**: 13 | **Risk**: MEDIUM
**Was**: BLOCKED (waiting for API)
**Now**: UNBLOCKED (API deployed 2025-02-01)
**Estimated**: 10 hours
**PRPROMPTS**: @PRPROMPTS/04-api_integration.md
**Dependencies**: Task 2.3 (DONE - unblocked 2025-02-01)
[Full task detail remains...]
### Task 3.2: Dashboard Widgets [TODO]
**Owner**: Dave (Mid) | **Story Points**: 8 | **Risk**: LOW
**Moved from**: Sprint 3 (capacity available)
**Estimated**: 6 hours
[Full task detail...]
```
## STEP 12: Save Updated Plan
Overwrite `docs/IMPLEMENTATION_PLAN.md` with updated content.
**Ensure**:
- All metadata updated
- Progress bars reflect actual status
- Burndown chart has new data
- Recommendations section added
- Sprint allocations revised
- Task statuses current
## STEP 13: Show Summary
Display update summary:
```
✅ Implementation Plan Updated
📄 File: docs/IMPLEMENTATION_PLAN.md
🔄 Updated: 2025-02-05 (after Sprint 2 complete)
📊 Progress:
Completed: 58 / 320 SP (18%)
Sprints Done: 2 / 11 (revised from 8)
Velocity: 29 SP/sprint (actual) vs 44 (planned)
📈 Velocity Analysis:
Sprint 1: 32 SP (100%)
Sprint 2: 26 SP (81%)
Average: 29 SP/sprint
Trend: Decreasing (team learning curve)
🚨 Blockers:
Task 2.3: API Foundation (RESOLVED 2025-02-01)
Affected Tasks: 3 tasks (26 SP) now unblocked
⏱️ Timeline:
Original: 16 weeks (8 sprints)
Revised: 22 weeks (11 sprints)
Delay: 6 weeks (38% behind)
💡 Recommendations:
1. Reduce scope (cut 2 P2 features) → 20 weeks
2. Add 1 senior dev → 18 weeks
3. Accept 22-week timeline
🔮 Forecast:
At current velocity (29 SP/sprint):
- Sprint 3-11: 9 sprints remaining
- Completion: Week 22 (2025-06-30)
🚀 Next Actions:
1. Review with Product Manager (timeline discussion)
2. Complete Sprint 3 (Week 5-6)
3. Run /update-plan again after Sprint 3
4. Consider scope reduction or resource addition
```
## Example: Before vs After
### Before (Initial Plan):
```
Total SP: 320
Planned Velocity: 44 SP/sprint
Sprints: 8 (16 weeks)
Completion: 2025-05-15
```
### After (Updated Plan):
```
Total SP: 320
Actual Velocity: 29 SP/sprint
Sprints: 11 (22 weeks)
Completion: 2025-06-30
Delay: 6 weeks
Reason: Lower velocity (66% capacity) + 1 week blocker
```
## Frequency
Run this command:
- **After each sprint completes** (every 2 weeks)
- **When major blocker resolved** (e.g., API deployed)
- **When significant delay detected** (task >2x estimate)
- **When team composition changes** (member added/removed)
## Notes
- This command is **read-heavy** (analyzes current state)
- It **recalculates** based on actual data, not assumptions
- Use `/generate-implementation-plan` for fresh plan, `/update-plan` for revision
- Velocity trends become reliable after 2-3 sprints
- Always discuss timeline changes with stakeholders before committing