### 9.0.11
Fix the issue where mergeCalendars merged customWeeks values incorrectly
Fix the error thrown in the onrender function when the column name includes spaces
Fix the issue where Gantt stayed in read-only mode after click_drag the Timeline when the S-Curve Overlay is enabled
Fix the issue where task duration was reset to 0 when using a Resource calendar and the Resources section is placed below the duration section of the Lightbox
Fix the console error triggered by the "This is a Trial version" warning when Gantt is used in React StrictMode
Fix the issue where the api/gantt_adjusttaskheightforbaselines function did not recalculate row height when gantt.config.baselines.render_mode is disabled
Fix the issue preventing tasks from being displayed when the Timeline is hidden in the Salesforce environment
Fix the issue where calendars are not inherited from parent tasks when dynamic_resource_calendars config is disabled
Fix the issue where scroll position reset on re-render when ReactGantt is in groupBy mode
Add the isSalesforce flag to gantt.env
Add the groupTasks prop to React Gantt
### 9.0.10
Fix the issue preventing changes to the parent field value in the Lightbox
Fix excessive scroll speed when using a mouse wheel in Firefox 88 and newer
Fix the inability to drag Project tasks when a subtask is unscheduled and lacks date parameters
Ensure gantt.render() is not called unexpectedly during the gantt.silent operation when using the open or close methods
Fix the issue where Project tasks are not repainted if the onBeforeTaskChanged event returns false
Ensure that task progress bars span the full width of the task when expected
Remove invalid WAI-ARIA attributes from read-only task links to improve accessibility
Fix the issue where task bar resizers do not adapt to changes in task bar height
### 9.0.9
Added examples of ReactGantt in the Commercial, Enterprice, Ultimate and Evaluation packages
Fix the issue where mouse wheel zooming stopped working after calling the resetLayout method
Fix the issue where the Quick Info popup appeared after clicking the expand/collapse button in the Timeline or Units views
Fix the script error that occurred when destroying Scheduler without the grid view initially rendered
Fix the error when loading a task with a non-existent parent while the Undo extension is enabled
Fix the issue where the click_drag extension did not work on touch devices
Improve grid scrolling experience on touch devices
### 9.0.7
Fix the error that occurs when clicking on a task in the timeline without a grid if keyboard_navigation is enabled
Correct WBS code calculation for sorted tasks that include a placeholder task
Resolve the issue where scale cells in the resource timeline disappear upon collapsing tasks or resizing the grid (placeholder url)
Ensure that the correct task order is maintained when adding both child and parent tasks inside the gantt.silent function
Preserve focus in editable resource cells after the value has been edited
Prevent Gantt from scrolling to the leftmost position of the grid when clicking on a task
Retain the group property when adding new tasks while in the group mode
Fix the issue where markers are not displayed if the timeline has been initially disabled
Prevent duplicate markers when the chart is not initially displayed in the layout configuration
Fix the disappearing of drag handles (link, progress, task resize) after dragging the timeline
Ensure the predecessor inline editor functions correctly when the link id type is numeric
Prevent duplication of the gantt_marker_area elements
Fix the undo functionality with the changeTaskId action
### 9.0.6
Fix the issue with the lightbox buttons not reflecting the current locale until reinitializing Gantt
Resolve the error occurring when deleting links if tasks are partially loaded
Prevent tasks from incorrectly moving to the bottom of their branch after changing the parent property type from numeric to string
Improve scrollbar behavior by adjusting the resizers near scrollbars
Ensure resource assignments persist correctly when adding tasks within gantt.batchUpdate
Fix task disappearance during drag-and-drop actions in the infinite scale
Ensure correct display of resource names in the lightbox after parsing data multiple times
Fix incorrect date calculation by getClosestWorkTime when using the duration_step config
Allow the onColumnDragMove event to be properly cancellable
Fix compatibility issue preventing the trial build from running in Lightning Web Components (LWC)
Resolve issues related to fetchTasks and deepcopy_on_parse configurations affecting the resource panel
Correct incorrect font icons appearance during Gantt initialization
### 9.0.5
Fix the error that occurs while resizing rows in the Resource Grid
Ensure the last year is specified in the range specified by the year_range property of the Time control
Correct the position of link arrows affected by the line-height CSS style
Fix the error that occurs while loading collections without the links array
Resolve the issue with gantt.config.baselines when it is falsy but not explicitly set to false
Fix the issue where click_drag doesn't work after calling resetLayout
Ensure selected child tasks are not displayed above their parent when keyboard_navigation is enabled
Fix keyboard navigation issues that occur when task IDs contain single quotes
Correct calculateEndDate behavior when the duration is negative
Resolve the error that occurs while loading datasets with baselines without an active timeline
Ensure grid cells are focused even when tasks fall outside the chart time range
Fix the error that occurs while partially deleting a date value in the inline editor
Fix the issue where the resource panel is displayed incorrectly after filtering when fetchTasks is enabled
### 9.0.4
Fix the issue where the SNET constraint date cannot be changed via the inline editor
Fix the issue where Gantt returns the global calendar instead of the resource calendar for tasks that have a single resource assignment when the dynamic_resource_calendars config is disabled
Fix the constraint date issue when changing the start date via the inline editor after reinitializing Gantt or resetting the layout
Fix the script error with some configurations of gantt.plugins when using the gantt.getGanttInstance method without specifying a container
Fix the issue where Gantt stops working when the auto_scheduling_project_constraint configuration is enabled, and tasks are grouped
Ensure Gantt retains the task constraint after dragging a task
### 9.0.3
Fix the regression in styles for the Quick Info popup
Resolve build warnings from PostCSS caused by the usage of 'start'/'end' instead of 'flex-start'/'flex-end'
Prevent resource assignment from being removed when updated via the lightbox
Fix the issue with an empty task array in resource_cell_value on non-working days when resource_render_empty_cells is enabled
Correct the error occurring when clicking on buttons embedded into sections of the lightbox
Ensure the resource panel and zoom levels remain in sync
Prevent Inline Editors events from being removed after reinitializing Gantt or resetting the layout
Fix the issue where the open state is not restored after redoing changes
### 9.0.2
Fix the regression causing incorrect styles for task borders and progress when the task color is specified via properties of a task object
Restore the functionality of the marker_class
Restore missing classname from the textarea section of the lightbox
Correct the issue where deadlines are displayed outside the task row and are not fully centered
Ensure that links are displayed above other links on mouse hover
Fix the issue where baseline dates are not calculated when loading them using the parse method
Correct positions of constrains for both regular and RTL views
Prevent unnecessary link loops when linking parts of split tasks
Fix the issue where Quick Info in detached mode is not hidden due to increased width and hardcoded styles
Update the Export API to support tree indentation for Excel export
Resolve the issue preventing task selection when the multiselect_one_level is enabled and a task on another tree level is selected
Updated type definitions
### 9.0.1
Fix the regression with the incorrect link position while dragging with smart_rendering enabled
Fix the regression where the Resource Control of the lightbox expands beyond its container
Correct the missing bottom border of time scale cells in the last row when cells are highlighted with custom CSS
Fix the incorrect behavior of sticky labels when smart_scales is disabled
Resolve the issue where Gantt continues vertically dragging a task after a right click
Fix the issue where calling resetLayout breaks the functionality of the S-Curve Overlay plugin
Prevent creation of duplicate links by the predecessor editor
### 9.0.0
Skins customization with CSS variables
New Dark skin is introduced
Built-in support for Baselines is added
Manually Scheduled Summary tasks are now supported
Sticky labels for time scales
Terrace skin is updated
Added support for Deadlines
Added default display of Constraints
Source files of skins are now included in the package
Add setUndoStack and setRedoStack methods to the Undo plugin for managing the undo/redo stacks
Ability to install the professional versions of the Gantt via npm
Bluebird Promise library is removed from the core library
Various improvements for scaling on high-definition screens and responsiveness on smaller screens
Updated type definitions
Fix the incorrect link positions for Milestones when the parent task has a larger height
Resolve the error that occurs during Auto Scheduling if auto-scheduling is canceled for a task
Ensure split tasks are properly displayed within the split parent row
Correct the Auto Scheduling of projects when a subtask link has a lag of 0
Fix incorrect link positions for split tasks that have different row heights
Ensure Gantt properly auto-schedules projects with 2 levels of tasks
Fix the issue where Gantt doesn't return the fixedDate "assignments" in the resource_cell_value when the task is outside the specified date range
### 8.0.11
Fix the Grid scrolling with the Timeline when a column resizer is present on the rightmost column
Prevent the lightbox from switching to the wide_form mode upon adding the Time section
Ensure the number editor respects min and max properties, preventing entry of values outside the defined range
Fix the error on deleting a task inside the gantt.batchUpdate method while tasks are displayed in the Resource Panel
Resolve the issue where tasks disappear after using keyboard shortcuts to indent or outdent multiple times
Correct the lightbox positioning to be properly centered in the Salesforce environment
Fix Keyboard navigation stopping due to the row_height setting
Correct the dates for project Auto Scheduling in some scenarios, so only one auto-scheduling call is needed for accurate results
Resolve the issue with Keyboard navigation when the Resource Histogram is present on the page
Fix the initialization error on touch-enabled devices when gantt.getGanttInstance is called with configuration parameters
The gantt.load method is removed from the Node.js version
Fix the error thrown by Gantt when defining a custom getVisibleRange function
Resolve the regression causing Gantt to scroll to a task after it is updated when Keyboard navigation is enabled
Ensure grid sorting works properly when clicking the sort icon in the header
Fix inconsistent task repainting when drag_timeline is enabled
### 8.0.10
Fix the issue where Gantt didn't merge date settings from the second Calendar
Fix the issue where Resources were not assigned when the "hide empty" option was enabled
Fix the getLightboxSection method returning a null for the Resource Section until any value was modified
Fix the issue where templates of the Resource Histogram were not called for tasks starting before the minimum date but ending within the displayed date range
Fix the issue where Resource Assignments were not saved after changing the task type
Fix the issue where the 'project' task type was not set in the lightbox
Fix the issue where worktime settings of the merged calendar were treated as weekends
Fix the issue that prevented grouping by resources when a task had Resource Assignments on different dates
Fix the error caused by attempting to filter split tasks with no children using the onBeforeSplitTaskDisplay event
Fix the issue where Resource Assignments were not updated after dragging the project with subtasks
### 8.0.9
Fix the issue that prevented reopening the Inline editor after vertically scrolling the Gantt
Fix the issue with DataProcessor ignoring custom headers specified in the gantt.createDataProcessor method
Fix tasks display issue that occurs when onBeforeLightbox handler returns false while creating a new task
Fix the incorrect markers height when timeline_placeholder config is enabled
Fix Formatter working only with Latin symbols
Fix the issue that causes tasks to disappear after vertically dragging a parent task
Fix the incorrect work of keyboard shortcut for scrolling when smart_rendering is enabled
Fix the issue with custom properties of Resource Assignments objects not being included after parsing
Update TypeScript type definitions
### 8.0.8
Fix the issue that caused the Undo extension to skip some actions in bulk operations
Fix the script error that occurs when gantt.deleteLink is called from the gantt.silent function
Fix the incorrect behavior of Auto Scheduling when two connected tasks have different calendars
Fix the script error that occurs after creating a circular link
Fix the script error that occurs after destroying the Gantt which has an editable Resource Panel
Fix the issue that caused the tooltip to disappear in some browsers
### 8.0.7
Fix the script error occurring in the trial build on SalesForce
The onAfterTaskUpdate event now fires before Auto Scheduling events after dragging tasks in the timeline
Fix the duplicate event firing while interacting with a selected task when the Multiselect extension is enabled
Fix the script error that happened when the first task in the chart did not contain dates
Add the lightbox section name as a class name to the section element for better identification
Fix the inability to unschedule tasks from the lightbox when Auto Scheduling is enabled
Fix the resize_rows marker positioning when scrolling the Gantt chart
Prevent Auto Scheduling of linked unscheduled tasks
Fix Gantt crash while adding Rollup tasks with disabled smart rendering
Fix dragging of split tasks on touch devices
Fix errors that occurred with the isCriticalTask, getFreeSlack, and getTotalSlack methods for unscheduled tasks
Fix the error occurring when a linked project contains only unscheduled child tasks
### 8.0.6
Enhancements and corrections in the usage of WAI-ARIA attributes for improved accessibility
Fix the issue of decreasing grid's width after repainting when the grid_elastic_columns config is enabled
The default number of undo_steps is increased from 10 to 100
The Export API client is now integrated into the GPL version of Gantt, previously it has been included only in PRO versions
Add support for the https export server endpoints in the Node.js version of Gantt
### 8.0.5
Fix incorrect warnings triggered by enabling extensions via the Gantt.getGanttInstance configuration.
Fix the incorrect work of gantt.exportToExcel when the skip_off_time config is enabled
Improvements for the Sample Explorer
### 8.0.4
Fix issue with DataProcessor not tracking changes of the Resource Datastore
Resolve an error that occurred after dragging a task when the process_resource_assignments config is disabled
Fix the incorrect work of gantt.calculateEndDate when subtracting dates in minute units
Minor performance improvement for layouts with visibility groups
### 8.0.3
Performance improvements for the Resource Panel
Fix incorrect calculation of Free Slack for tasks with a negative Lag
Fix incorrect calculation of Critical Path for tasks with 100% progress
### 8.0.2
Fix Export errors that happen when LinkFormatters are used.
Fix the incorrect work of the Undo extension with Resources and Resource Assignments
Type definitions are updated
Performance improvements for Rollup tasks rendering
Performance improvement for Split Tasks rendering
Other performance improvements
### 8.0.1
Fix an error thrown from "gantt.showCover()" called when the lightbox is not opened
Fix regression in split tasks which caused a script error for the split tasks displayed outside of the time scale
Fix regression in the "gantt.addLinkLayer()" method
Fix the incorrect work of auto scheduling with MSO, FNET, and FNLT constraints when the settings of work time contain a minute part
Fix work of the "onBeforeSplitTaskDisplay" event on scroll
### 8.0.0
Updated Resource Management:
Resources and resource assignments can now be loaded together with the data
Changes of resources and resource Assignments can be captured using the DataProcessor
Reduced amount of boilerplate code required to use the Resource panel
Grouping tasks functionality now can preserve the original Gantt tree structure inside groups
Empty state screen
The ability to extend the background grid of the timeline to the whole container
Improvements for rollup items and split tasks:
The ability to style separate rollup items and split tasks
The ability to hide all rollup items from the project task
The ability to control where rollup items are displayed
The ability to filter split tasks
Performance optimization for display of split tasks
The ability to delete items only after receiving confirmation from the backend
New deleteAfterConfirmation parameter of the dataProcessor configuration object
Updated Auto Scheduling & Constraint calculation
Tasks now can inherit the constraint type from parent projects
Improvements for Critical Path, Slack and Auto Scheduling
Critical path, Slack and Auto scheduling algorithms can now use progress of a task
Total slack can now be calculated for projects
Major performance improvement of critical path calculation
The getTaskBy() method now allows selecting 'project' tasks
The ability to put any HTML content into the cells of the Timeline
The export API is included into gantt.plugins and no longer requires adding additional JS file. Check the Migration article
Fix the duration calculation issue with minute duration_unit and custom working time settings
Fix various issues with slack calculation
Fix the script error on data loading when Slack calculations are enabled
SetWorkTime method now supports setting rules for dates inside customWeeks
Fix the issue with smart rendering that causes blank spaces instead of data in the Gantt
Fix the issue with vertical reordering of rows in the Grid when some rows have custom heights
Fix the incorrect work of Inline editors when the Multiselect extension is enabled
Fix the incorrect display of Quick Info popup when gantt.config.quick_info_detached config is set to false
Correct arguments of is_valid function of Inline Editor interface. The function now receives the column object
Ensure the parent property of task is saved correctly when the task is created with gantt.groupBy active
Fix the issue with unexpected vertical scroll when placeholder tasks and Keyboard navigation are enabled
Fix the issue with DataProcessor causing some changes not to be set to the backend after Auto Scheduling
Fix the incorrect work of vertical reordering, which allowed task rows to being dragged outside the Gantt
Fix the incorrect order of odd CSS classes of rows in the Resource panel
### 7.1.13
Fix the incorrect work of the "gantt.addLinkLayer()" method with the "smart_rendering" property
Fix issues with display of S-Curve Overlay together with different time scales
Fix the issue with resizing of grid columns when the "grid_elastic_columns" property is enabled
Fix the issue that caused Gantt to reset the position of the vertical scroll after deleting a task using Keyboard Navigation
Fix the incorrect work of the "treeDatastore.move()" method
Fix the issue with the "gantt.parse()" method, extra collections from the dataset should be available via the "gantt.serverList()" method
Fix the issue with the "gantt.groupBy()" method, which caused the selection state to reset after grouping
Fix compatibility issues with Vue.js v3.x
Fix the script error thrown from the "gantt.getConstraintLimitations()" method when the specified task didn't have 'constraint_date'
Fix compatibility issues with SalesForce Web Security
Fix the issue which caused focus to be returned to the Gantt after clicking outside the Gantt container when Keyboard Navigation was enabled
German locale is updated
Now it is possible to open the inline editor after one click on a task in the multi-selection mode (the "inline_editors_multiselect_open" property is added)
### 7.1.12
Fix the incorrect work of the gantt.isWorkTime() method with the "week" time unit
Fix the issue that prevented tasks and links from being rendered when they were added via the gantt.silent() method
Fix the issue that caused the "Task not found" error message to be shown after data loading in some cases
Fix the incorrect work of the gantt.changeLightboxType() method that left old lightbox elements in DOM
Fix the incorrect calculation of the end dates of tasks when the tasks overlap after the Summer/Winter clock change
Fix the issue that caused the Resource Grid to disappear when the user edited a resource value using the cell editor
Fix the script error that happened when the Gantt layout contained the "resourceGrid"/"resourceTimeline" views but not included the "grid"/"timeline" views
Fix the incorrect work of the autosize config when the Gantt layout contained Resource Panel
Fix the lightbox for split tasks, the lightbox now should be displayed when you double-click on a split task
### 7.1.11
Fix sourcemaps for compressed Gantt files
Fix the incorrect position of markers when autosize = 'y' was applied
Fix the incorrect position of the tooltip and some other elements of Gantt in cases when the Gantt container had extra margin or vertical offsets
Fix the issue that caused rows of the editable resource diagram to change the order after the first cell of the resource assignment was edited
Fix the issue that caused the incorrect work of the smart rendering after expanding or collapsing of tasks in some cases
Fix the issue with the onBeforeDrag event which didn't block the default actions when the click_drag and drag_timeline extensions were activated
Fix the script error that fired when the changeId() method was called for the resource assignments store
Scrollbars of the default Gantt layout no longer require fixed scrollVer/scrollHor names to work correctly
Split tasks now receive the 'gantt_selected' class on selection, in the same way as regular tasks do
### 7.1.10
Fix the issue which caused Gantt not to render a project task if it didn’t have children and the start_date parameter was specified for the task
Fix the issue with resizing a task row by drag and drop if the task ID was either a non-number value or a numeric string with more than 16 symbols
Fix the incorrect work of visibility groups which prevented the sizes of the grid and time scale from being synchronized in the complex layout
Fix the issues with task dates after dragging several tasks horizontally at once
Fix the issue which caused dataProcessor not to send all updates from different datastores when the auto-update mode is disabled
Fix the issue which caused the milestone with the FF link to be moved to the next day
Fix the incorrect calculation of the end_date of milestones when using backward scheduling and setting project_end to the non-working time
Fix the incorrect work of task reordering if HTML elements were displayed above the gantt
Fix the issue with the unsetWorkTime() method when the date/day configuration was removed from the calendar but the changes were not applied immediately
Fix the issue with the clearAll() method which didn’t clear selected tasks if the multiselect extension was enabled
Fix the error appeared when applying the exportToExcel() method with the visual: true parameter and setting the duration_unit config to ‘hour’
### 7.1.9
Fix the issue with alignment of subtasks after dragging a project in the "year" scale and switching between scales dynamically
Fix the issue which caused the duration of the project to change after dragging the project with subtasks in the "month" scale
Fix the issue with Auto Scheduling that caused the constraint type to be changed from "ASAP" to "SNET" after changing the duration of the task
Fix the incorrect work of backward scheduling after changing the start and end dates via inline editors when schedule_from_end is enabled
Now it is possible to open the lightbox for read-only tasks in the read-only mode
Now it is impossible to edit read-only tasks via the lightbox
Fix the issue with the lightbox which caused it not to open for editable tasks in the read-only mode (appeared in v6.3.1)
Fix the issue with resizing columns in grid after hiding the timeline via show_chart
Fix the issue with Auto Scheduling which couldn't be canceled after changing values of project_start and project_end
Fix the issue which caused the gantt to assign constraints to the tasks with disabled auto-scheduling
Fix the issue with defining a year range by the lightbox when the range of dates of tasks is more than 10 years and a range for the year selector isn't specified
Fix the script error that was thrown after loading Gantt if a horizontal scrollbar was attached to 3 or more vertical views
Fix the incorrect work of the onBeforeTaskAutoSchedule event after setting the ASAP constraint for the task without links when the strict mode is enabled
Fix the error occurred when running minified versions of Gantt in Next.js projects
Fix the issue which caused the width of Gantt to be changed after initializing the gantt instance inside an empty container
### 7.1.8
Fix the script error that was thrown from the gantt.groupBy method when the Resource Histogram and fit_tasks config were enabled
Fix the incorrect work of the Undo extension that didn't send updates to the server when vertical reordering was reverted
Fix the issue with the Export to MS Project module which in some cases caused an Unknown error result when custom properties were sent to the export
Fix the incorrect work of the gantt.silent method, which did not prevent gantt.changeTaskId from triggering API events and repaints
Fix the incorrect work of the gantt.undo method that did not restore the original vertical position of the reverted item
Fix the incorrect work of the resource assignment form which caused gantt to replace the user-provided id of the resource assignment with an auto-generated value
Fix the incorrect work of gantt.changeTaskId in cases when the affected tasks had nested items, which caused the level of nested items to be calculated incorrectly
### 7.1.7
Fix issues with incorrect calculation of the total slack values
Performance improvement for total slack calculation
Style fixes for the lightbox in the Material skin
Fix the issue with the Zoom plugin that prevented the zoom.init method from working when calling the method after gantt.init
Fix the script error that happened when using the inherit_calendar config together with the gantt.groupBy method
Fix the script error thrown when adding tasks via gantt.bathUpdate if the placeholder task is active
Fix the issue that allowed the placeholder task to be sorted, reordered, or accept subtasks
Fix issues with incorrect size of grid columns
Fix the incorrect work of the column's resizers which conflicted with reordering of the columns
### 7.1.6
Fix the incorrect work of the auto_scheduling_move_projects config when schedule_from_end is enabled
Fix the incorrect work of the onrender callback of the column which caused custom elements to disappear when the grid is scrolled quickly
Fix the regression (appeared in v7.1.5) which caused rows of the grid to disappear after the grid cell is resized in complex layouts
Fix the incorrect work of the size/visibility groups which prevented the sizes of columns from being synchronized in the complex layout
Improved the display of the grid when the gantt is rendered in a small container
### 7.1.5
Fix the incorrect work of vertical reordering of tasks in the "marker" mode when gantt rows have different heights
Fix the issue with the sizes of the timeline and the grid in some layouts when the "show_grid" and "show_chart" configs are disabled
The "data-column-name" and "data-column-index" attributes are added for cells of the grid header
Fix the incorrect display of the grid after re-initialization of the gantt after removing all columns from the config
Fix the issue that caused the resource panel configuration to overwrite the main configuration of the gantt in Vue.js applications
Added the ability to modify the configuration of the resource panel on the fly by modifying the configuration object provided to the resource layout
### 7.1.4
Fix the incorrect work of unsetWorkTime that caused affected dates to have incorrect work hours
Fix the script error thrown in the Resource histogram after scrolling the histogram when resource_render_empty_cell is set to false and smart_rendering is enabled
Fix the incorrect work of the editNextRow and editPrevRow methods of the Inline Editors module
Fix the incorrect work of the Quick Info popup that caused the popup to be displayed after clicking on the "add" button in the grid
Fix the incorrect work of the ASAP constraints that caused tasks not to be moved to the earliest date of the project
Fix the incorrect work of Inline Editors that prevented constraints from being edited via the inline editor
Fix the incorrect behavior of the "scroll into view" logic of Keyboard Navigation which called an unnecessary scroll when selected task bars are visible
Fix the script error thrown when the mouse is moved outside the container when the click_drag extension is enabled
Performance improvements for the auto_types configuration option of Gantt
### 7.1.3
Fix the script error thrown on gantt.moveTask call when some tasks are hidden via the onBeforeTaskDisplay event
Fix the issue with the speed of the scroll in the latest Firefox browser
Performance improvement for calculations of working time
### 7.1.2
Major performance improvement of the resource panel
Fix the script error thrown when gantt.destructor is called while gantt.load is in progress
Fix the incorrect behavior of split tasks on change of the task id
Fix the incorrect work of scroll on mouse wheel in Angular
### 7.1.1
Fix the regression in the click_drag plugin
Fix the Security Violation error thrown from the gantt when setting the gantt.config.csp config to the "auto" mode
Fix code build settings that caused the package code v7.1.0 to contain ES6 syntax, the library is again ES5 compatible
Fix the script error fired when trying to resize a grid column when gantt.config.reorder_grid_columns config is enabled
Update TypeScript type definitions
Add the onDestroy event to DataStore
Performance improvement for gantts with a large number of task calendars
Performance improvement for calculations of resource assignment during batchUpdate and autoScheduling
### 7.1.0
The ability to assign resources to the specific dates of the task
The new gantt.getTaskAssignments() method
The ability to manage the resource assignments via the new gantt.config.process_resource_assignments and gantt.updateTaskAssignments() Gantt API
Rollup tasks and milestones
The ability to hide task bars and milestones in the timeline area
The ability to set different working hours for different time spans
The ability to set the height for a separate row in the grid
The ability to resize a row in the grid by drag-and-drop
The ability to get the height of the DOM element of the task via the gantt.getTaskBarHeight() method
New events: onBeforeRowResize, onRowResize, onBeforeRowResizeEnd, onAfterRowResize
The onrender callback for rendering a grid cell into DOM is added
The onrender callback for rendering a custom element of the task layer into DOM is added
Fix the issue with reordering tasks vertically in the resource view when resources have values assigned
Fix the issue that caused “resource_cell_value” not being called and the resource markers not being rendered if a task doesn’t start at the beginning of the timeline cell
Fix the issue that caused Gantt to stop working when deleting the task with the id that already exists in the data store
Fix the script error thrown when specifying the 0 number value as a task id even if the “root_id” parameter is set
Fix the issue that caused the resizer listener not to work in Salesforce environment
Fix the script error appeared when applying Fullscreen Extension several times together with its methods
Fix the issue with Keyboard Navigation Extension that caused navigation in Grid to stop working when adding the plugin several times
Fix the issue with Inline Editors when the editor couldn't be opened in a cell that is located after a column that is hidden via hide:true property
### 7.0.13
Fix the script error happened when the layout configuration is changed dynamically and gantt.addTaskLayer is used
Fix the issue with the initial inner height of the resource histogram when the fetchTasks option is used
Fix the incorrect work of the predecessor editor which caused it to delete existing links when the value is edited
Fix the incorrect work of the gantt when a task with a non-unique ID is added to the gantt via the gantt.addTask and gantt.parse methods
Performance improvement for drag and drop when the auto_types and drag_project configuration options are enabled
Performance improvement for calculation of working time when duration_unit is set to "day"
### 7.0.12
Fix some minor issues with vertical drag and drop in large projects
Fix the issue with the incorrect size of the container when the "autosize" config is used
Keyboard navigation should now work correctly with the horizontal scroll of the grid
HTML views of Layout now support external scrollbars
Fix the issue that caused the incorrect state of the grid after reordering tasks, if the additional grid was added to the layout
Fix the script error that happened after clearing and reloading the resource panel if a resource was selected
Add the ability to disable automatic correction of the end date in the time section of the lightbox, which was applied when the selected start date was greater than the end date
Fix a typo in the default config of Duration Formatter
Fix the script error thrown when the gantt is destroyed while a popup message is shown
Fix the initial position of the horizontal scroll in Grid and Timeline in the RTL mode
Fix the incorrect work of the lightbox which caused the selected type of a task not to be saved if the typeselect control was not added to the lightbox configuration
Fix the issue that caused markers to disappear after calling the "gantt.resetLayout()" method
Fix the performance issue with the "drag_project" config used in large projects
Fix the issue that prevented the QuickInfo popup from being displayed in the read-only mode when custom buttons were added to the config
### 7.0.11
Add the container_resize_timeout config for changing the timeout before redrawing Gantt when resizing the container
Add the wheel_scroll_sensitivity config for changing the speed of scrolling the gantt by the mouse wheel
Fix the bug with Auto Scheduling when using different working calendars
Fix the conflict between placeholder tasks and Auto Scheduling
Fix redundant repaints when api/gantt_sort_config.md is enabled
Fix the issue with Inline Editors and a scrollable grid, when inline editors lose focus right after click
Fix the issue that caused Gantt to close the Quick Info popup when the user clicks on it
### 7.0.10
Fix the incorrect work of vertical resizers (the regression appeared in v7.0.9)
Prevent unexpected page refresh which happened during vertical reordering of tasks on Android Chrome (pull-to-refresh)
Fix the script error which fired during creating a link on mobile Firefox
Fix the incorrect work of task selection when the multiselect config is enabled but the multiselect plugin is not activated
Improve the work of HTML select controls inside Inline Editors
Fix the incorrect work of Auto Scheduling when linked tasks use different work calendars
The gantt.plugins method will not activate plugins which are specified with false value
Fix the conflict between Inline Editors and Keyboard Navigation
Fix the issue that caused Inline Editors to close on double click
### 7.0.9
Fix the script error on the second initialization of Gantt when custom datastores are added
Fix the incorrect work of auto-scheduling when using with FF and SS links and when the source and target tasks use different working calendars
Fix the incorrect calculation of working time when duration_unit is set to "minute" and the start time is set to the middle of a non-working day
Fix touch support for Safari iPad on iPadOS v13.6
Fix the sizes of the Lightbox modal overlay on mobile devices
Fix the incorrect display of lightbox buttons in some browsers
Fix support of Italian and Portuguese locales in the gantt.i18n module
Fix the bug in the Parent control of the Lightbox which caused the incorrect work when tasks were assigned to the root level
Fix the script error which happened when initializing a gantt inside an iframe
Fix the incorrect work of the redo config when the undo config is disabled
### 7.0.8
- Fix some issues with touch support on Android/iOS devices
- Fix regression (appeared in v7.0.6) with link creation and gantt.isLinkAllowed method
- Fix the script error which was thrown when the 'locale' parameter was used in gantt.getGanttInstance
- Fix the script error that was thrown from gantt.destructor when the Keyboard Navigation and the Quick Info extensions were used
### 7.0.7
- Fix the syntax error in type definition of gantt.Promise
### 7.0.6
- Fix script errors that were fired on touch devices during drag and drop
- Fix the incorrect work of the Auto Scheduling extension when types of links were defined using numeric values
- Reduced the number of redundant repaints of the resource histogram
- Performance improvements for the task grouping extension
- Fix the ability to scroll a resource timeline on touch devices
- Fix the incorrect work of the resource control when the 'hide empty' button is used
- The return type of gantt.Promise in type definitions is fixed
### 7.0.5
- Performance improvements for work time calculation when the duration_unit config is set to "hour"
- Performance improvements for work time calculation when the duration_unit config is set to "minute"
- The ability to specify working calendars in the configuration object of Gantt.getGanttInstance is added
### 7.0.4
- Removed the 10000px limit on the gantt size in the autosize mode, which should allow printing larger charts
- Drag and drop now finishes when the user releases the mouse button over any part of the document body rather than over the gantt container only
- Portuguese locale was updated
- The return type of gantt.columnIndexByDate in type definitions is fixed
- Fix script errors that were fired when the Gantt instance was destroyed during drag and drop
- Fix the incorrect calculation of end_date/duration when duration_unit is set to "minute" and the last worktime interval finishes after 23:00
- Fix the issue which caused groups of the grouping extension to expand whenever the user modified any task
- Fix the issue which caused the second parameter of dataProcessor.setTransactionMode to be ignored if an object was passed into the first parameter
- Fix the issue which caused the active inline editor to disappear after repaint of Gantt
- Fix the issue with the static_background extension which caused mouse click on empty cells to be interpreted as a click on task elements
- Gantt now dynamically repaints links between split tasks during drag and drop
- Fix the script error which was thrown from gantt.addTask in node.js package
- Fix the script error which was thrown from gantt.destructor in node.js package
### 7.0.3
- Fix regression in the setWorkTime method which caused a script error when the working time is set for a specific day
- Fix the incorrect work of the Keyboard Navigation extension when Gantt is used inside a SalesForce Lightning Web Component
### 7.0.2
- Fix the incorrect work of date formatters when gantt.config.csp is set to true.
- Fix regression in the Click Drag and Drag Timeline extensions which caused the incorrect work when multiple instances of Gantt were created
- Fix the incorrect css class of a task row element after returning the error status from the dataProcessor router function
- Fix the incorrect work of inline editors inside Shadow DOM
### 7.0.1
- Major performance improvement for calculation tasks' duration in the working minutes
- Fix regression in the Tooltip and Undo extensions which caused the incorrect work when multiple instances of Gantt were created
- Fix the issue with the reordering of grid columns which caused the timeline to scroll when a mouse pointer moved to the edge of the grid during drag and drop
- Fix the incorrect position of the column after its dragging and dropping to the right side of the grid border
- dataProcessor custom router should now work correctly with rejected promises
- Fix the regression in smart rendering which caused some links not to be visible
- Split tasks now display not only the first level children but also all nested subtasks
- Fix the issue with split tasks and smart rendering which happened when a split task had the 'task' type
- Fix the issue with split tasks which caused the gantt not to calculate the duration of the 'project' tasks nested in a split task
- Fix the incorrect position of a placeholder after opening an inline editor in the RTL mode
### 7.0.0
- Nodejs-compatible build of dhtmlxGantt is now available
- Update TypeScript type definitions
- Extensions and Locales are now bundled with dhtmlxgantt.js core file and are enabled from config
- Ability to specify work time in minutes
- Ability to merge several work time calendars
- Changed default work hours from 8:00-17:00 to 8:00-12:00, 13:00-17:00
- Simpler format for entering work time intervals for Calendars
- Extend the API of the QuickInfo extension
- CSP mode is enabled by default
- All custom HTML attributes were changed to `data-` attributes
- Add the ability to use `text-overflow:ellipsis` on grid cells
- Add the ability to reorder grid columns by drag and drop
- Add support for 'elastic' column width for the scrollable grid
- gantt.templates.xml_date/gantt.templates.xml_format were replaced with gantt.templates.parse_date/gantt.templates.format_date
- gantt.config.xml_date was replaced with gantt.config.date_format
- Fix the bug which caused a column to change width after hiding and showing the column again
- Fix the bug which disabled the ability to select any task when the multiselect extension was disabled via the `multiselect` config
- Fix the incorrect work of `gantt.sort` for tasks with equal start dates
- Fix drag and drop of a link when Gantt is initialized inside a Web Component
### 6.3.7
- Significant performance improvement for smart rendering of chart and resource panel
### 6.3.6
- Fix the regression in gantt.resetLayout which caused the script error
- Fix the issue with the QuickInfo popup which caused it to be positioned behind the resource panel in some cases
- Fix the script error thrown from the gantt.getShortcutHandler method
- Fix the script error thrown from the tooltip.show(x, y) method
- gantt.getTaskNode now returns the correct HTML element for split tasks
- Fix the issue with horizontal scrollbars not being displayed when visibility groups are specified in some layout configurations
### 6.3.5
- Fix the issue with task grouping which caused vertical scroll position to reset after moving any task with drag and drop
- Fix the script error which happened when drag_timeline config was set to null
- Fix the incorrect position of highlighted cells when static_background and static_background_cells are enabled and smart_rendering is disabled
- Fix the issue with the onAfterBranchLoading event not being called
- Fix the incorrect work of smart rendering when the value of task_height is less than the value of row_height
- A public method for rebuilding gantt layout after changing its config is added
### 6.3.4
- Fix crashes of the resource load diagram when smart rendering is switched off
- Fix issue with the custom task property named "unit", as gantt considered it as a duration unit value and multiplied the task duration after its dragging
- Fix the incorrect Tooltip position when the autosize config is enabled
- Fix the incorrect alignment behavior of grid cells when both the scrollable property and autofit config are set to true
- Creating a link between a task in the timeline and a placeholder in the grid is now blocked
- Fix the bug with the auto scheduling extension that caused gantt to freeze when a task has the constraint type (SNET/FNET/SNLT/FNLT) with no date specified, or with an invalid date
### 6.3.3
- Fix the incorrect resizing behavior of grid that disabled the Timeline in some cases
- gantt.parse should now correctly update the project tree when a parent task is loaded after its children
- Fix compatibility with SalesForce Lightning Aura components framework (Evaluation build)
- Fix the incorrect position of the Tooltip in SalesForce environment
- Fix the incorrect Tooltip position when the gantt container has a vertical margin
- Add missing WAI-ARIA attributes to elements inside the gantt
- Fix the incorrect work of the min_duration config
- Fix the incorrect work of link formatters with custom instances of the gantt
### 6.3.2
- Fix the script error which happened when gantt.destructor was called when the click-drag feature was enabled
- gantt.parse no longer modifies data objects passed into arguments, deep copies are made instead
- TypeScript type definitions were updated
- onBeforeBranchLoading and onAfterBranchLoading public events were added so it would be possible to modify the url or dynamic parameters of dynamic loading requests
- Added a public method for changing the url of the dataProcessor after its initialization
### 6.3.1
- Fix the regression in the smart rendering which caused links not to be rendered in some cases.
- Fix the bug that allowed modifying and creating new tasks with keyboard navigation when the read-only mode is activated
- Fix the display issue with Fullscreen extension which allowed some page elements to be displayed over the gantt in the fullscreen mode
- Fix the bug that caused the drag-timeline extension to reset the value of the readonly config
### 6.3
- Ability to specify decimal units for the duration of tasks
- Ability to scroll the timeline via mouse click and drag
- Ability to drag and drop multiple tasks horizontally
- Ability to display tasks outside the explicit start_date and end_date range of the time scale
- Add a new task_end_date template for formatting end dates of tasks
- Ability to add custom actions to the Undo stack
- Ability to connect custom layers to smart rendering
- Inline editors for predecessors now support formatted values of links
- Remove default limits for input values in date inline editors
- Ability to specify the root node for the Fullscreen extension
- Ability either to change or disable horizontal scroll by shiftKey+mousewheel
- Roboto font was removed from Material skin and has to be imported manually
- Fix crashes of the resource histogram when smart rendering is switched off
- Fix compatibility with r.js compressor
- Fix various conflicts between keyboard navigation and inline editors
- Fix the incorrect state of the DataProcessor when tasks and links were modified sequentially from a custom router
- A correct data object of Task/Link is now also passed into delete call of a custom router
### 6.2.7
- Fix the issue with vertical resizing of grids with horizontal scroll in complex layouts
- Fix the incorrect work of the resource histogram when the scale step is greater than one
- Fix the reopened bug with collapsed branches after calling gantt.parse from v6.2.4 bugfix
### 6.2.6
- Fix the regression in v6.2 Smart Rendering which in some cases caused incorrect vertical positions of tasks after re-initialization of the Gantt
- Fix the issue with QuickInfo popup not being displayed for unscheduled tasks
- Fix incorrect work of extension files with the Ultimate build of Gantt
### 6.2.5
- Fix incorrect initial values of subtasks in the onBeforeTaskChanged event handler after dragging a project with subtasks
- Fix incorrect work of the grouping extension when auto task types are enabled
- Fix the script error after returning the false value from th