# Delivery Metrics Catalog
## Purpose
Define concrete metrics for tracking software delivery performance, team efficiency, and engineering excellence.
**Scope**: DORA metrics, velocity, flow, and quality-adjusted delivery
**Target Audience**: Project Managers, Build Engineers, DevOps Engineers, Metrics Analysts
**Integration**: Reference this catalog when populating Measurement Plan metric inventory
## Overview
Delivery metrics answer: **How efficiently are we shipping value?**
**Categories**:
1. **DORA Metrics** - Industry-standard software delivery performance (4 metrics)
2. **Velocity Metrics** - Predictable capacity and throughput (3 metrics)
3. **Flow Metrics** - Work efficiency and bottleneck identification (3 metrics)
**Philosophy**: Measure outcomes (features delivered) not outputs (lines of code written)
**Critical Balance**: Speed (deployment frequency, lead time) must balance with Quality (change failure rate, defect escape rate)
## DORA Metrics
### Background
DORA (DevOps Research and Assessment) research identifies 4 key metrics predicting high-performing software teams:
1. Deployment Frequency
2. Lead Time for Changes
3. Change Failure Rate
4. Mean Time to Recovery (MTTR)
**Source**: Annual State of DevOps Reports (Google Cloud, DORA research team)
**Validation**: Proven correlation with business outcomes (profitability, productivity, customer satisfaction)
**Elite vs Low Performers**: Elite teams deploy **multiple times per day** with **< 1 hour** lead time and **< 15%** change failure rate. Low teams deploy **< once per month** with **> 6 months** lead time and **> 45%** failure rate.
### Metric 1: Deployment Frequency
**Definition**: How often code is deployed to production
**Why It Matters**:
- Indicates team's ability to deliver value frequently
- Small, frequent deployments reduce risk
- Faster feedback loop from users
**Data Source**: CI/CD pipeline logs, deployment tracking system
**Collection Method**:
**GitHub Actions**:
```bash
gh api repos/:owner/:repo/deployments \
--jq '[.[] | select(.environment == "production" and .created_at > (now - 7*86400 | todate))] | length'
```
**CI/CD Log Query**:
```bash
grep "deploy.*production.*success" /var/log/ci.log | wc -l
```
**SQL Example**:
```sql
SELECT COUNT(*)
FROM deployments
WHERE environment = 'production'
AND deployed_at >= CURRENT_DATE - INTERVAL '7 days'
```
**Formula**: Count production deployments / time period
**Targets (DORA Benchmarks)**:
| Performance Level | Deployment Frequency |
|-------------------|---------------------|
| Elite | Multiple per day |
| High | Once per day to once per week |
| Medium | Once per week to once per month |
| Low | Less than once per month |
**Thresholds for Alerting**:
- Warning: < 1 deployment per week (Construction phase)
- Alert: < 3 deployments per month
- Critical: Deployment frequency drops 50% from baseline
**Recommended Review Cadence**:
- Track: Daily (team dashboard)
- Review: Weekly (iteration planning)
- Analyze: Monthly (process improvements)
**Related Metrics**:
- Deployment success rate (% deployments that succeed)
- Deployment duration (time to execute deployment)
- Rollback frequency (% deployments requiring rollback)
**Agent Automation**:
- Auto-query CI/CD API for deployment counts
- Generate deployment frequency trend charts
- Alert if frequency drops below threshold
### Metric 2: Lead Time for Changes
**Definition**: Time from code commit to production deployment
**Why It Matters**:
- Measures efficiency of delivery pipeline
- Long lead times indicate process bottlenecks
- Short lead times enable faster market response
**Data Source**: Version control (Git) + CI/CD logs + deployment tracking
**Collection Method**:
**Python Example**:
```python
from datetime import datetime
def calculate_lead_time(commit_sha, github_api, cicd_api):
# Get commit time
commit = github_api.get_commit(commit_sha)
commit_time = commit['commit']['author']['date']
# Get deployment time
deployment = cicd_api.get_deployment_for_commit(commit_sha)
deploy_time = deployment['deployed_at']
# Calculate lead time
lead_time = (deploy_time - commit_time).total_seconds() / 3600
return lead_time
```
**SQL Example**:
```sql
SELECT
pr.id,
d.deployed_at - pr.first_commit_time AS total_lead_time,
pr.merge_time - pr.first_commit_time AS code_complete_time,
d.deployed_at - pr.merge_time AS deployment_lag
FROM pull_requests pr
JOIN deployments d ON d.commit_sha = pr.merge_commit_sha
WHERE d.deployed_at > NOW() - INTERVAL '30 days'
ORDER BY total_lead_time DESC
```
**Formula**: Deployment time - Commit time
**Lead Time Components** (for bottleneck analysis):
1. Coding Time: First commit to PR opened
2. Review Time: PR opened to PR approved
3. Merge Lag: PR approved to merged
4. CI/CD Time: Merge to build complete
5. Deployment Time: Build complete to production deploy
**Targets (DORA Benchmarks)**:
| Performance Level | Lead Time |
|-------------------|-----------|
| Elite | Less than 1 hour |
| High | 1 day to 1 week |
| Medium | 1 week to 1 month |
| Low | More than 1 month |
**Thresholds for Alerting**:
- Warning: Lead time > 5 days (Construction phase)
- Alert: Lead time > 10 days
- Investigation: Lead time doubles from baseline
**Recommended Review Cadence**:
- Monitor: Daily (CI/CD dashboard)
- Review: Weekly (identify bottlenecks)
- Trend Analysis: Monthly (process improvements)
**Bottleneck Identification**:
| Stage | Target | Threshold | Common Issues |
|-------|--------|-----------|---------------|
| Code Review | < 4 hours | > 24 hours | Too few reviewers, large PRs |
| CI/CD Pipeline | < 15 min | > 30 min | Slow tests, serial execution |
| Deployment Wait | < 1 hour | > 4 hours | Manual approvals, limited deploy windows |
**Related Metrics**:
- Cycle time (work started to done, different from lead time)
- Code review queue depth (leading indicator)
- Build duration (CI/CD efficiency)
**Agent Automation**:
- Auto-calculate from Git + CI/CD data
- Identify bottleneck stage automatically
- Recommend process improvements
### Metric 3: Change Failure Rate
**Definition**: Percentage of production deployments causing failure (requiring rollback, hotfix, or incident)
**Why It Matters**:
- Measures quality of releases
- High failure rate indicates insufficient testing or rushed deployments
- Balances speed (deployment frequency) with quality
**Data Source**: Deployment logs + incident management system
**Collection Method**:
**Python Calculation**:
```python
def calculate_change_failure_rate(deployments, incidents):
total_deployments = len(deployments)
failed_deployment_ids = set(
i['caused_by_deployment_id']
for i in incidents
if i['caused_by_deployment_id']
)
failed_deployments = len(failed_deployment_ids)
failure_rate = (failed_deployments / total_deployments) * 100
return round(failure_rate, 2)
```
**SQL Example**:
```sql
SELECT
COUNT(DISTINCT d.id) AS total_deployments,
COUNT(DISTINCT CASE WHEN i.id IS NOT NULL THEN d.id END) AS failed_deployments,
ROUND(100.0 * COUNT(DISTINCT CASE WHEN i.id IS NOT NULL THEN d.id END) / COUNT(DISTINCT d.id), 2) AS failure_rate
FROM deployments d
LEFT JOIN incidents i ON i.deployment_id = d.id AND i.severity IN ('critical', 'high')
WHERE d.environment = 'production'
AND d.deployed_at > NOW() - INTERVAL '30 days'
```
**Formula**: (Failed deployments / Total deployments) × 100
**What Counts as Failure**:
1. Rollback: Deployment reverted within 24 hours
2. Hotfix: Emergency fix deployed within 24 hours
3. Incident: Production incident (SEV1/SEV2) caused by deployment
4. SLO Breach: Deployment causes SLO violation
**Targets (DORA Benchmarks)**:
| Performance Level | Change Failure Rate |
|-------------------|---------------------|
| Elite | 0-15% |
| High | 16-30% |
| Medium | 31-45% |
| Low | Greater than 45% |
**Thresholds for Alerting**:
- Warning: Failure rate > 20% (last 10 deployments)
- Alert: Failure rate > 30%
- Critical: 2 consecutive deployment failures
**Recommended Review Cadence**:
- Track: Per deployment (immediate feedback)
- Review: Weekly (identify failure patterns)
- Deep Dive: Monthly (process improvements)
**Root Cause Categories** (track for pattern analysis):
| Failure Type | Example | Prevention |
|--------------|---------|------------|
| Insufficient Testing | Bug escaped QA | Increase test coverage |
| Config Error | Wrong environment variable | Config validation in CI |
| Dependency Issue | Upstream API changed | Contract testing, version pinning |
| Infrastructure | Resource exhaustion | Capacity planning, load testing |
| Human Error | Wrong deployment sequence | Automation, runbooks |
**Related Metrics**:
- Deployment success rate (inverse: 100% - failure rate)
- Test coverage (should be inverse correlated)
- Pre-production defect catch rate
**Agent Automation**:
- Auto-correlate deployments with incidents
- Categorize failure types
- Recommend prevention strategies
### Metric 4: Mean Time to Recovery (MTTR)
**Definition**: Average time to restore service after production incident
**Why It Matters**:
- Measures operational resilience
- Fast recovery minimizes customer impact
- Indicates effectiveness of incident response and runbooks
**Data Source**: Incident management system (PagerDuty, Jira Service Desk, OpsGenie)
**Collection Method**:
**SQL Query**:
```sql
SELECT
AVG(resolved_at - detected_at) AS avg_mttr,
PERCENTILE_CONT(0.5) WITHIN GROUP (ORDER BY resolved_at - detected_at) AS median_mttr,
PERCENTILE_CONT(0.95) WITHIN GROUP (ORDER BY resolved_at - detected_at) AS p95_mttr
FROM incidents
WHERE severity IN ('critical', 'high')
AND resolved_at IS NOT NULL
AND resolved_at > NOW() - INTERVAL '30 days'
```
**Python Example**:
```python
def calculate_mttr(incidents):
recovery_times = []
for incident in incidents:
if incident['severity'] in ['critical', 'high'] and incident['resolved_at']:
delta = incident['resolved_at'] - incident['detected_at']
recovery_times.append(delta.total_seconds() / 3600)
if not recovery_times:
return None
return {
'mean_hours': sum(recovery_times) / len(recovery_times),
'median_hours': sorted(recovery_times)[len(recovery_times) // 2],
'max_hours': max(recovery_times),
'incident_count': len(recovery_times)
}
```
**Formula**: (Resolution time - Detection time) averaged across incidents
**MTTR Components** (for bottleneck analysis):
1. Detection Time: Issue occurs to alert fires
2. Response Time: Alert fires to responder engaged
3. Diagnosis Time: Responder engaged to root cause identified
4. Fix Time: Root cause identified to fix deployed
5. Validation Time: Fix deployed to service confirmed healthy
**Targets (DORA Benchmarks)**:
| Performance Level | MTTR |
|-------------------|------|
| Elite | Less than 1 hour |
| High | 1 hour to 1 day |
| Medium | 1 day to 1 week |
| Low | More than 1 week |
**Thresholds for Alerting**:
- Warning: MTTR > 4 hours (critical incidents)
- Alert: MTTR > 1 day
- Process Review: MTTR increases 50% from baseline
**Recommended Review Cadence**:
- Track: Per incident (immediate postmortem)
- Review: Weekly (identify bottleneck stages)
- Trend Analysis: Monthly (process improvements)
**Bottleneck Analysis Table**:
| Stage | Target | Common Issues |
|-------|--------|---------------|
| Detection | < 5 min | Insufficient monitoring, alert fatigue |
| Response | < 15 min | Unclear on-call, poor escalation |
| Diagnosis | < 30 min | Poor observability, no runbooks |
| Fix | < 2 hours | No rollback plan, manual processes |
| Validation | < 15 min | No automated health checks |
**Related Metrics**:
- Mean Time to Detect (MTTD): How fast do we notice?
- Mean Time to Acknowledge (MTTA): How fast do we respond?
- Mean Time Between Failures (MTBF): How often do incidents occur?
**Agent Automation**:
- Parse incident tickets, calculate MTTR
- Identify bottleneck stages automatically
- Generate runbook improvement recommendations
## Velocity Metrics
### Metric 5: Story Point Velocity
**Definition**: Story points completed per iteration
**Why It Matters**:
- Predicts team capacity for planning
- Enables roadmap forecasting
- Indicates team health (consistent = healthy, erratic = problems)
**Data Source**: Project management tool (Jira, Linear, GitHub Projects)
**Collection Method**:
**Jira API Example**:
```python
from jira import JIRA
def get_velocity(jira_client, sprint_id):
jql = f'sprint = {sprint_id} AND status = Done'
issues = jira_client.search_issues(jql)
velocity = sum(
int(issue.fields.customfield_10016 or 0)
for issue in issues
)
return {
'sprint_id': sprint_id,
'velocity': velocity,
'issue_count': len(issues)
}
```
**Formula**: Sum of story points for all stories marked "Done" in iteration
**Baseline Establishment**:
- Measure for 3-5 iterations to establish baseline
- New teams: volatile velocity (estimation calibration)
- Mature teams: stable velocity (±10% variance)
**Targets**:
- No universal target (varies by team size, story point scale)
- Process Target: Stable velocity (±10% variance) within 3 iterations
- Improvement Target: 5-10% increase per quarter (skill growth, process improvement)
**Thresholds for Alerting**:
- Warning: Velocity drops > 20% from average
- Alert: Velocity drops > 30% from average
- Investigation: Velocity variance > 30% for 2 consecutive iterations
**Recommended Review Cadence**:
- Calculate: End of each iteration
- Review: Iteration planning (trend analysis)
- Forecast: Quarterly planning
**Common Issues**:
| Velocity Pattern | Diagnosis | Action |
|------------------|-----------|--------|
| Consistently low | Overcommitment | Reduce iteration scope |
| Erratic (high variance) | Estimation inconsistency | Estimation workshop, WIP limits |
| Declining trend | Accumulating tech debt | Address debt, refactoring |
| Increasing rapidly | Gaming estimates | Recalibrate estimation |
**Related Metrics**:
- Throughput (# stories completed, complements velocity)
- Commitment accuracy (planned vs completed points)
- Velocity per person (team efficiency)
**Agent Automation**:
- Auto-query Jira/Linear API for velocity
- Detect velocity anomalies
- Forecast completion dates
### Metric 6: Throughput
**Definition**: Number of work items (stories, tasks, bugs) completed per iteration
**Why It Matters**:
- Complements velocity (measures output, not estimated effort)
- Less gameable than story points
- Useful when estimates are inconsistent
**Data Source**: Project management tool
**Collection Method**:
**SQL Query**:
```sql
SELECT
iteration_id,
COUNT(*) AS throughput,
COUNT(*) FILTER (WHERE type = 'Story') AS stories,
COUNT(*) FILTER (WHERE type = 'Bug') AS bugs,
COUNT(*) FILTER (WHERE type = 'Task') AS tasks
FROM work_items
WHERE status = 'Done'
AND completed_date >= iteration_start_date
AND completed_date <= iteration_end_date
GROUP BY iteration_id
ORDER BY iteration_id
```
**Formula**: Count of work items transitioned to "Done" during iteration
**Baseline**: Measure for 3-5 iterations (typical: 8-12 items per 2-week iteration for 5-person team)
**Targets**:
- No universal target (depends on item size, team size)
- Process Target: Stable throughput over time
- Balance: More items = smaller slices = faster feedback (generally good)
**Thresholds for Alerting**:
- Warning: Throughput drops > 30% from average
- Alert: Throughput < 5 items per iteration (may indicate large, slow items)
**Recommended Review Cadence**:
- Calculate: Iteration end
- Review: Alongside velocity for holistic view
**Use Cases**:
- Kanban teams: Throughput more relevant than velocity
- Bug fixing: Count bugs fixed per week
- Cross-team comparison: More standardized than story points
**Related Metrics**:
- Average item size (velocity / throughput)
- Work item age (created to done time)
### Metric 7: Cycle Time
**Definition**: Time from work start to completion (in-progress to done)
**Why It Matters**:
- Indicates work efficiency
- Identifies bottlenecks
- Predicts when current work will complete
**Data Source**: Project management tool workflow transitions
**Collection Method**:
**Jira Changelog Query**:
```python
def get_cycle_time(jira_client, issue_key):
issue = jira_client.issue(issue_key, expand='changelog')
in_progress_time = None
done_time = None
for history in issue.changelog.histories:
for item in history.items:
if item.field == 'status':
if item.toString == 'In Progress' and not in_progress_time:
in_progress_time = history.created
elif item.toString == 'Done':
done_time = history.created
if in_progress_time and done_time:
return (done_time - in_progress_time).days
return None
```
**Formula**: Done time - In Progress time
**Targets**:
- Small items: < 3 days
- Medium items: 3-7 days
- Large items: 1-2 weeks (should be decomposed)
**Thresholds for Alerting**:
- Warning: Cycle time > 10 days for any item
- Alert: Cycle time > 10 days for 3+ items simultaneously
- Investigation: Average cycle time increases 50%
**Recommended Review Cadence**:
- Monitor: Daily (identify stuck items)
- Review: Weekly (process improvement)
**Use Cases**:
- Identify work stuck in progress
- Find bottlenecks (coding, review, testing stages)
- Forecast completion (items in progress with historical cycle time)
**Related Metrics**:
- Lead time (request to delivery, includes wait time)
- Work in Progress (WIP) - inversely correlated with cycle time
## Flow Metrics
### Metric 8: Work In Progress (WIP)
**Definition**: Number of work items simultaneously in progress
**Why It Matters**:
- High WIP indicates context switching, slow completion
- Low WIP enables focus, faster flow
- Leading indicator (predicts velocity drop before it happens)
**Data Source**: Project management board
**Collection Method**:
**SQL Query**:
```sql
SELECT COUNT(*)
FROM work_items
WHERE status IN ('In Progress', 'In Review', 'In Testing')
AND iteration_id = CURRENT_ITERATION
```
**By Person**:
```sql
SELECT assignee, COUNT(*) AS wip_count
FROM work_items
WHERE status IN ('In Progress', 'In Review')
GROUP BY assignee
HAVING COUNT(*) > 2
```
**Formula**: Count items in active states (In Progress, In Review, In Testing)
**Targets**:
- Team WIP Limit: Team size × 1.5 (e.g., 5-person team = 7-8 WIP limit)
- Individual WIP Limit: 1-2 items per person
- Pull-Based Flow: New work only started when WIP drops below limit
**Thresholds for Alerting**:
- Warning: WIP > team limit
- Alert: WIP > team limit for 2+ days
- Action: Stop starting new work, finish existing items
**Recommended Review Cadence**:
- Monitor: Daily (real-time dashboard)
- Review: Daily standup
- Adjust: Quarterly (based on retrospective)
**Impact of High WIP**:
- Increased cycle time (items take longer)
- Context switching overhead
- Delayed feedback
- Lower quality (rushing to juggle items)
**Related Metrics**:
- Cycle time (should decrease when WIP decreases)
- Throughput (should increase when WIP controlled)
**Agent Automation**:
- Monitor WIP continuously
- Alert when limit exceeded
- Recommend which items to finish first
### Metric 9: Code Review Queue Depth
**Definition**: Number of pull requests (PRs) awaiting review
**Why It Matters**:
- Leading indicator of delivery slowdown
- Long queue = delayed merges = longer lead time
- High queue = bottleneck in review process
**Data Source**: Version control system (GitHub, GitLab, Bitbucket)
**Collection Method**:
**GitHub API**:
```bash
gh api repos/:owner/:repo/pulls \
--jq '[.[] | select(.draft == false and .review_comments == 0)] | length'
```
**Python Example**:
```python
def get_review_queue(repo, github_token):
headers = {'Authorization': f'token {github_token}'}
url = f'https://api.github.com/repos/{repo}/pulls'
prs = requests.get(url, headers=headers).json()
queue_by_reviewer = {}
for pr in prs:
if pr['draft'] or pr['merged_at']:
continue
for reviewer in pr['requested_reviewers']:
name = reviewer['login']
queue_by_reviewer[name] = queue_by_reviewer.get(name, 0) + 1
return queue_by_reviewer
```
**Formula**: Count open, non-draft PRs awaiting review
**Targets**:
- Team Queue: < 5 PRs awaiting review
- Per Reviewer: < 3 PRs assigned to any individual
- Age: No PR waits > 24 hours for first review
**Thresholds for Alerting**:
- Warning: Queue depth > 5 PRs
- Alert: Queue depth > 10 PRs
- Critical: Any PR waiting > 48 hours
**Recommended Review Cadence**:
- Monitor: Continuously (real-time dashboard)
- Review: Daily (identify stuck PRs)
- Adjust: Weekly (review capacity)
**Bottleneck Indicators**:
- Queue growing: Review capacity insufficient
- Specific reviewers overloaded: Review responsibility imbalance
- PRs stuck for days: PR too large or unclear
**Related Metrics**:
- Code review time (PR opened to approved)
- PR size (lines changed, inversely correlated with review speed)
**Agent Automation**:
- Monitor review queue depth
- Identify overloaded reviewers
- Assign reviewers based on capacity
### Metric 10: Build Duration
**Definition**: Time to execute CI/CD build pipeline
**Why It Matters**:
- Long builds slow feedback loop
- Leading indicator of delivery issues
- Build duration creep indicates technical debt
**Data Source**: CI/CD system (GitHub Actions, Jenkins, CircleCI, GitLab CI)
**Collection Method**:
**GitHub Actions**:
```bash
gh api repos/:owner/:repo/actions/runs \
--jq '.workflow_runs[] | {id, conclusion, duration: (.updated_at | fromdateiso8601) - (.run_started_at | fromdateiso8601)}'
```
**Formula**: Build end time - Build start time
**Targets**:
- PR Validation: < 10 minutes (fast feedback)
- Main Branch: < 15 minutes
- Full Release Build: < 30 minutes
- Trend: Duration should not increase > 10% per quarter
**Thresholds for Alerting**:
- Warning: Build duration > 15 minutes
- Alert: Build duration > 20 minutes
- Critical: Build duration > 30 minutes or +50% from baseline
**Recommended Review Cadence**:
- Monitor: Per build (CI dashboard)
- Review: Weekly (identify slow stages)
- Deep Dive: Quarterly (optimization sprint)
**Bottleneck Analysis**:
| Build Stage | Target | Common Issues |
|-------------|--------|---------------|
| Checkout | < 30 sec | Large repo, no shallow clone |
| Dependencies | < 2 min | No caching, too many deps |
| Compilation | < 3 min | No incremental builds |
| Unit Tests | < 5 min | Slow tests, serial execution |
| Integration Tests | < 5 min | Heavy tests, no parallelization |
| Package/Deploy | < 2 min | Large artifacts, slow registry |
**Optimization Strategies**:
- Parallelize test execution
- Cache dependencies
- Incremental builds
- Prune slow tests (move to nightly suite)
**Related Metrics**:
- Build success rate (% builds that pass)
- Flaky test rate (tests intermittently fail)
**Agent Automation**:
- Analyze build logs, identify slow stages
- Recommend parallelization opportunities
- Detect build duration regression
## Summary Table
| Metric | Category | Data Source | Frequency | Elite Target | Agent Auto-Collectable |
|--------|----------|-------------|-----------|--------------|------------------------|
| Deployment Frequency | DORA | CI/CD Logs | Daily | Multiple/day | Yes |
| Lead Time for Changes | DORA | Git + CI/CD | Per Deploy | < 1 hour | Yes |
| Change Failure Rate | DORA | Deploys + Incidents | Per Deploy | 0-15% | Partial |
| MTTR | DORA | Incident System | Per Incident | < 1 hour | Yes |
| Story Point Velocity | Velocity | Jira/Linear | Per Iteration | Stable ±10% | Yes |
| Throughput | Velocity | Jira/Linear | Per Iteration | Stable | Yes |
| Cycle Time | Velocity | Jira/Linear | Per Item | < 3 days | Yes |
| Work In Progress (WIP) | Flow | Jira/Linear | Daily | 1.5 × team size | Yes |
| Code Review Queue Depth | Flow | GitHub/GitLab | Continuous | < 5 PRs | Yes |
| Build Duration | Flow | CI/CD System | Per Build | < 10 min | Yes |
## Integration with SDLC Framework
### Phase-Specific Metrics
**Inception**:
- Focus: Estimation accuracy, risk identification rate
- Minimal delivery metrics (no code yet)
**Elaboration**:
- Focus: Velocity baseline, architecture spike completion
- Track: Story point velocity (establish baseline), cycle time
**Construction**:
- Focus: All DORA + velocity + flow metrics
- Track: Full suite (10 metrics above)
**Transition**:
- Focus: DORA metrics (especially MTTR, change failure rate)
- Track: Deployment frequency, production incident metrics
### Template Integration
**Measurement Plan**: Populate metric inventory with metrics from this catalog
**Status Assessment**: Report velocity, throughput, cycle time (Section 4), change failure rate, build duration (Section 5)
**Iteration Assessment**: Compare planned vs actual velocity (Section 3), include build success rate (Section 6)
## Conclusion
Delivery metrics provide objective evidence of team performance and process health. These 10 metrics form the foundation for data-driven decision making in software delivery.
**Next Steps**:
1. Select metrics appropriate to current phase
2. Establish baselines (measure for 3 iterations)
3. Automate collection (manual measurement fails)
4. Review regularly (metrics without action are waste)
5. Iterate (adjust as project matures)
**Critical Success Factors**:
- Measure outcomes, not outputs
- Automate collection
- Set thresholds to trigger action
- Review trends, not point-in-time values
- Balance speed with quality